Sikafloor®-306 W
2-PART PUR MATT SEAL COAT PART OF THE SIKA COMFORTFLOOR® FLOORING RANGE
Sikafloor®-306 W is a two part water based, very low VOC, polyurethane, matt seal coat.
- Water based
- Very low odour
- Good UV and yellowing resistance
- Easy to clean
Usage
Matt seal coat for Sika ComfortFloor® flooring rangeAdvantages
- Water based
- Very low odour
- Good UV and yellowing resistance
- Easy to clean
Packaging
Part A | 8.5 Kg |
Part B | 1.5 Kg |
Part A+B | 10 Kg |
Colour
Part A | white, liquid |
Part B | yellowish, liquid |
Sikafloor®-306 W is matt after final curing.
Product Details
ENVIRONMENTAL INFORMATION
Conformity with LEED v2009 IEQc 4.2: Low-Emitting Materials - Paints and Coatings
Chemical Base
Polyurethane
Shelf Life
Part A | 6 months from date of production |
Part B | 12 months from date of production |
Storage Conditions
The product must be stored properly in original, unopened and undamaged sealed packaging, in dry conditions at temperatures between +5 °C and +30 °C.
Density
Part A | ~ 1.05 kg/l |
Part B | ~ 1.13 kg/l |
Mixed resin | ~ 1.07 kg/l (diluted with ~ 5 -10 % water) |
All Density values at +23°C
Abrasion Resistance
~11 mg | CS10 /1000/1000 |
Tensile Strength
~ 18 MPa (14 days / +23 °C) | (DIN 53504) |
Chemical Resistance
Sikafloor®-306 W is resistant to many chemicals. Contact Sika technical service for specific information.
Application
Mixing Ratio
Part A : Part B = 85 : 15 (by weight)
Ambient Air Temperature
+10 °C min. / +30 °C max.
Relative Air Humidity
75 % max.
During curing the humidity should not exceed 75 % max. Adequate fresh air ventilation must be provided to remove the excess moisture from the curing
product.
Dew Point
Be aware of condensation!
The substrate and uncured floor must be at least 3 °C above dew point to reduce the risk of condensation or blooming on the floor finish.
Substrate Temperature
+10 °C min. / +30 °C max.
Pot Life
Temperature | Time |
+10 °C | ~ 50 minutes |
+20 °C | ~ 30 minutes |
+30 °C | ~ 20 minutes |
Caution: End of potlife is not noticeable.
Curing Time
Before overcoating Sikafloor®-306 W allow:
Substrate temperature | Minimum | Maximum |
+10 °C | 26 hours | 4 days |
+20 °C | 16 hours | 3 days |
+30 °C | 12 hours | 2 days |
Based on relative humidity of max. 75 % and good ventilation. Times are approximate and will be affected by changing ambient conditions particularly temperature and relative humidity.
Applied Product Ready for Use
Temperature | Foot traffic | Light traffic | Full cure |
+10 °C | ~ 30 hours | ~ 48 hours | ~ 6 days |
+20 °C | ~ 16 hours | ~ 24 hours | ~ 4 days |
+30 °C | ~ 12 hours | ~ 18 hours | ~ 3 days |
Note: Times are approximate and will be affected by changing ambient conditions
Consumption
~0.13 kg/m²/layer
These figures are theoretical and do not allow for any additional material due to surface porosity, surface profile, variations in level and wastage etc.
MIXING
Prior to mixing, stir part A mechanically. When all of part B has been added to part A, mix continuously for 3 minutes until a uniform mix has been achieved. To ensure thorough mixing pour materials into another container and mix again to achieve a consistent mix. After mixing give the material a rest for 10 minutes. Over mixing must be avoided to minimise air entrainment.
Mixing Tools:
Sikafloor®-306 W must be thoroughly mixed using a low speed electric stirrer (300 - 400 rpm) or other suitable equipment.
APPLICATION
Prior to application, confirm substrate moisture content, relative humidity and dew point. Uniformly spread Sikafloor®-306 W by using a short pile nylon roller. Sikafloor®-306 W can also be applied by using a airless spray equipment. A seamless finish can be achieved if a “wet” edge is maintained during application.
CLEANING OF TOOLS
Clean all tools and application equipment with water immediately after use. Hardened and/or cured material can only be removed mechanically.
CLEANING
Please refer to “Sikafloor®- CLEANING REGIME”.